PDE Submission Timetable


NEW CONTRACT EFFECTIVE JANUARY 1, 2011

CY Data Submission Type Submission Timeline
2011 EDI Agreement and Submitter Application Deadline October 31, 2010
2011 Certification Complete* January 31, 2011
2011 First Production File Due** March 31, 2011
Comply with routine production timeline thereafer
2011 Production Submission Ongoing Monthly Submissions
March 31, 2011 - June 29, 2012
  • Originals within 30 days following Date of Service or Date Claim Received, whichever is greater.
  • Adjustments and deletions resubmitted within 90 days following date of discovery.
  • Rejected records resubmitted within 90 days following receipt of rejected status from CMS.
2011 Final Submission Deadline June 29, 2012 (11:59 p.m. Eastern Time)
2011 Direct & Indirect Remuneration
(DIR) Submission Dealine
June 29, 2012 (11:59 p.m. Pacific Time)
*Only new contracts submitting directly or new third party submitters submitting in CY2011 must complete the testing and certification process.
** Applies to new contract effective at the beginning of the year.